Detailed Implementation Timeline: Northern Ireland Good Friday Agreement

« Back to Accord

Detailed Implementation Timeline: Northern Ireland Good Friday Agreement

Implementations

Detailed Implementation Timeline – 1998

Provision related to replacing the 1985 Anglo-Irish Agreement as well as provision related to referendum in both places. However, the decommissioning of all paramilitary organizations did not happen in 1998.

Detailed Implementation Timeline – 1999

While referendum provision and constitutional change provision met the initial implementation timeline, decommissioning of paramilitary did not happen within two years.

Detailed Implementation Timeline – 2000

No developments observed this year.

Detailed Implementation Timeline – 2001

No developments observed this year.

Detailed Implementation Timeline – 2002

No developments observed this year.

Detailed Implementation Timeline – 2003

No developments observed this year.

Detailed Implementation Timeline – 2004

No developments observed this year.

Detailed Implementation Timeline – 2005

The decommission process was completed in 2005.

Detailed Implementation Timeline – 2006

No further developments observed.

Detailed Implementation Timeline – 2007

No further developments observed.